The MBTA plans to rebuild Newtonville Commuter Rail Station with elevators, accessible platforms and a pedestrian bridge, replacing a station entrance system that relies on stairs.
Early construction work, including site preparation and utility relocation, is scheduled to begin in January 2027, with completion projected for June 2029, according to the MBTA’s project information.
The Framingham/Worcester Line station would receive two high-level side platforms connected by a bridge with elevators and stairs. Improvements also include track and signal work, canopies, benches, tactile warning strips, signs, bicycle racks and pick-up and drop-off areas.
The MBTA plans to maintain service during most construction, with two anticipated closures: approximately three months in 2027 and two months in 2029. The Harvard Street entrance would provide access to a modified section of the existing platform, while the Walnut Street entrance would remain closed during construction.
Riders should check MBTA updates for closure dates and alternative travel arrangements as work approaches.
The project combines state and federal funding. Rep. Jake Auchincloss secured $7 million in federal Community Project Funding to improve Newton’s commuter rail accessibility, according to a November 2024 state announcement.
Similar accessibility improvements at West Newton and Auburndale remain dependent on additional funding.
Residents can follow the project on the MBTA website or contact [email protected].