The League of Women Voters Newton is pushing the City Council to approve $2 million in local funding for a 35-unit affordable housing project in Newton Highlands.
The group sent a letter Nov. 11 to the council's Zoning and Planning and Finance committees urging them to approve Community Preservation Act (CPA) funds for the proposed apartment building at 1186 Walnut Street, according to a post on the LWVN website.
The project, developed by 1186 Walnut LLC and sponsored by Terra Living Partners, would create a 100% income-restricted rental building in Ward 6. Michael Alperin, founder and president of Terra Living Partners, leads the effort. Arx Urban serves as the development consultant.
What the project includes
The building would hold 1 studio, 19 one-bedroom, 11 two-bedroom and 4 three-bedroom apartments. Twelve units would be reserved for households earning at or below 30% of the area median income (AMI), 17 for those at or below 60% AMI and 6 for those at or below 80% AMI, according to the CPA funding proposal.
The total project budget is roughly $26.8 million. The $2 million CPA request would fill the remaining local funding gap. The rest would come from federal and state low-income housing tax credit equity, a first mortgage and state subordinate debt.
The Newton Affordable Housing Trust voted Aug. 20 to commit $150,000 to the project and recommended the developer seek the remaining local funds through the CPA program. Peter Sargent, vice chair of the trust, signed the commitment letter.
By-right under village center zoning
The site sits within Newton's Village Center Overlay District (VC3). The city's planning department confirmed the design is a compliant, by-right development that requires no special permit, variance or parking relief, according to the funding proposal.
That makes it one of the first projects of its kind under Newton's updated Village Center Overlay District zoning law, according to the trust's commitment letter.
The building would be all-electric, built to Passive House standards and equipped with rooftop solar. Ground-floor retail space would front Walnut Street. The site is a block from the Newton Highlands Green Line station.
Timeline and next steps
The Community Preservation Committee held a public meeting on the project Oct. 13. The developer's state funding application was due Dec. 3, and the project team had requested evidence of local financial commitment ahead of that deadline.
If state funding is awarded, the developer anticipates a financial closing in the fourth quarter of 2027. Construction would run from the third quarter of 2027 through the first quarter of 2030, according to the proposal's timeline.